72nd / Luther Safety Improvements

Traffic engineers evaluated operations for vehicles, pedestrian and bicycles and identified low-cost improvements to reduce the number and severity of crashes at the intersection. The intersection will converted to an all-way stop. The intersection at Bell and Alberta will also be reconfigured.

Status

Complete

Updated: March 15, 2023

Why

To reduce crashes and improve safety for all roadway users.

Schedule

  • Design: July 2021 - Jan. 2023
  • Construction: March 2023 - May 2023

Funding

  • Project estimate $27,000.
  • Funding is provided from county road funds and HB2017 state gas taxes. 
Contact
Department Staff
Christian Snuffin
Transportation and Development
503-742-4716

Phone:503-742-4691
Email:engineering@clackamas.us

150 Beavercreek Road Room #325 Oregon City, OR 97045

Office Hours:

Monday to Thursday
8 a.m. to 4 p.m.

Available by phone/email
Friday
8 a.m. to 3 p.m.

Related Events
Transportation Engineering
-
Transportation Maintenance, Transportation and Development, Transportation Engineering
-