Henrici Road Storm Water Improvements

Project Description: To reduce the chance of a future landslide in the project area, a new storm water collection, detention and conveyance system will be constructed. To ensure the safety of the construction crews and the travelling public, please observe the speed limits and drive safely.

Updated: 10/01/15

Status: Henrici Rd project has been redesigned to construct the new storm system. Construction on site began the week of June 15, 2015 and was complete by the 21st of August, in time for school to start without traffic delays. All of the work is complete now.

Clackamas County and Subcom Excavation & Utilities (the contractor) would like to thank you for driving safely and patiently through the work zone.


Contacts: Kerri Whitlow, Project Manager: (503) 742-4680 or

Contractor: Subcom Excavation & Utilities, LLC Hillsboro, Oregon

Things to be aware of:

Funding: The $500,000 project is being funded with Federal Emergency Relief Funds.

You may be interested to know:

Share this page

Development Services Building

Contact Us

Transportation Engineering
150 Beavercreek Rd
Oregon City, OR 97045

(503) 742-4691

M-TH: 8 a.m.-4 p.m.
F: 8 a.m.–3 p.m.

Report a Road Concern