Rugg Road Landslide Repairs

In early 2021, heavy rains and strong winds toppled trees, causing the slope to collapse next to Rugg Road near the Hideaway Court intersection in the Boring area. A retaining wall will be built at this location.

Temporary protective sheeting and plant seeding are in place until permanent repairs are constructed.

Status

Project design complete

Updated: Nov. 21, 2023

Why

To stabilize the slope next to Rugg Road.

Schedule

After receiving construction proposals much higher than our engineering estimates, we intend to advertise the project for construction bids in the spring. We will update the construction schedule as we have more information.

  • Design: March 2021 - March 2022
  • Construction: Spring 2024 - Fall 2024

Traffic impacts

Single-lane closures will be needed during construction. A temporary road closure is anticipated for 3–4 weeks to build the wall.

Current activities

Project design complete.

Funding

  • Project estimate $970,000
  • Funding is provided from Damascus road funds

Stay In Touch

 

Phone:503-742-4691
Email:engineering@clackamas.us

150 Beavercreek Road Room #325 Oregon City, OR 97045

Office Hours:

Monday to Thursday
8 a.m. to 4 p.m.

Available by phone/email
Friday
8 a.m. to 3 p.m.

Related Events
Transportation Maintenance, Transportation and Development, Transportation Engineering
-
Related News
DTD, Library District, Development Agency, Transportation Engineering