Central Point and New Era Intersection Enhancements

Project description: The intersection of Central Point and New Era has a high ranking in the Safety Priority Index System (SPIS) list. There have been a number of crashes including some fatal and serious injury crashes at the intersection. This project may include changes such as intersection lane realignment, addition of flashers, pavement markings and/or signing, and deployment of electronic warning devices.

Updated: 4/13/18

Status: In design

Schedule:

  • Construction start: June 2020
  • Construction complete: October 2020

Contact: Jonathan Hangartner, PE, Project Manager, jhangartner@clackamas.us, 503-742-4649

Things to be aware of:

  • There will be vehicle traffic impacts during construction of this project.

Current activities:

  • Intersection realignment geometric alternatives analysis and design

Funding:

  • Project estimate is $593,000
  • Funding is provided from Clackamas County Road Funds.