Wright Road (Dave Phillips Bridge)/Woodcock Creek Scour Repair Project

Project description: Stabilize the low-flow channel in Woodcock Creek upstream of Wright Road, stabilize the high-flow spillway and the Wright Road Bridge structure, and reduce flood risk on Woodcock Creek upstream and downstream of Wright Road. The “Dave Phillips Bridge” is experiencing erosion around the high-flow spillway and on both bridge abutments. Grading and drainage improvements are also necessary. The project includes installing temporary access roads, installing erosion countermeasures, introducing logs for habitat enhancement, grading the historic and high-flow channels, and installing riparian area plantings.

Updated: 01-09-20

Status: Site work will begin after all permits and approvals are acquired and during the in-water work window of June 1 to September 30, 2020

Schedule:

  • To be completed by September 30, 2020

Contact: Devin Patterson, Project Manager, devinpat@clackamas.us or 503-742-4666

Things to be aware of:

  • There may be delays of up to 20 minutes, but a complete road closure is not anticipated.

Current activities:

  • Completion of regulatory permit applications
  • Development of 100% Plans & Specifications

Funding:

  • County Road Fund

Phone:503-742-4691
Email:engineering@clackamas.us

150 Beavercreek Road Room #325 Oregon City, OR 97045

Office Hours:

⚠ Visit our Closures page for the latest information about office closures.
We also encourage you to call before visiting any county office.