The stormwater system located along the Mt. Scott Trail is full of roots and has eroded, causing it to no longer function as it should. Clackamas Water Environment Services (WES) is planning to repair the failing stormwater pipe. The repair work will include:
- Repairing approximately 200 feet of storm pipe
- Raising one manhole
When
Summer 2022. Construction is expected to begin late June and may take up to four weeks. On weekdays, work hours will be limited to 7 a.m. to 6 p.m. If work is necessary on a weekend, the schedule would be 8 a.m. to 5 p.m.
Impact
During this work, every effort will be made to minimize the impact on your neighborhood. However, please be aware that a portion of the Mt. Scott Trail between SE Adoline Way and SE Nella Way will be closed during construction.