El Camino Way Stormwater Improvements

Status

Project is in design phase.

Updated: Nov. 16, 2023

Increasing stormwater capacity to reduce flooding and improve maintenance access

Flooding on El Camino Way, El Centro Way, El Centro Ct and La Mesa Way roads in the Oak Grove area occurs periodically. To reduce the frequency of flooding and to provide stormwater infrastructure with capacity for a 10-year storm event, we will replace the existing stormwater pipes. Currently, most of the stormwater pipes exist on private property and most of the pipes will be moved to existing roads within the public right of way. Constructing the storm pipes within the right of way will be easier to maintain.

Why

To decrease the frequency of flooding, improve maintenance access, and to comply with Oak Lodge Water District and Clackamas County standards requiring stormwater collection systems to provide for a 10-year storm event for this size of drainage basin.

Schedule

  • Design: Feb. 2023 to April 2024
  • Right of way: Dec. 2023 to April 2024
  • Construction: May 2024 to Oct. 2024

Traffic impact

  • Expect shoulder and lane closures and detours with delays up to 20 minutes during construction.

Current activities

  • Project planning and solicitation of design services.

Funding

  • Project estimate $1.4 million 
  • Funding is provided from American Rescue Plan Act (ARPA) funds.

Phone:503-742-4691
Email:engineering@clackamas.us

150 Beavercreek Road Room #325 Oregon City, OR 97045

Office Hours:

Monday to Thursday
8 a.m. to 4 p.m.

Available by phone/email
Friday
8 a.m. to 3 p.m.

Related Events
Transportation Engineering
-
Transportation Maintenance, Transportation and Development, Transportation Engineering
-