Pedestrian crossings serving Oak Grove Elementary School currently do not meet Americans with Disabilities Act (ADA) requirements and lack visibility in the Oak Grove area.
This project will install a flashing crosswalk at the intersection of SE Oak Grove Blvd and Arista Road. Improvements will also include replacing curb ramps, and adding new safety signs, pavement markings and street lighting.
Improvements at SE River Road and SE Courtney Ave will also include replacing curb ramps, and adding new safety signs, pavement markings and street lighting.
Why: to improve safety for students traveling to Oak Grove Elementary and for people with disabilities. To comply with Americans with Disabilities Act (ADA) requirements.
Schedule
- Project planning and design: Winter 2026– Winter 2027
- Right of Way: Summer 2026 – Winter 2027
All right of way acquisitions are conducted as required by state and federal law. - Construction: Summer 2027 – Fall 2027
Traffic Impact
- No impacts to traffic at this time. Rolling single lane closures and detours may be needed during construction.
Project is expected to take up to 4 months to complete.
Current Activities
- Project design
- Right-of-way
Funding
- Project estimate $957K
- Funding is provided from a Safe Routes to School (SRTS) grant and county road funds