Preparing for construction
Updated: July 16, 2026
Project description
Install a flashing crosswalk at the intersection of Oregon Trail Elementary and 152nd Ave in the Oregon City area. Improvements will also include new safety signs, pavement markings and street lighting.
Schedule
- Construction: August 2026 – October 2026
Traffic impact
- Expect shoulder and lane closures with minimal delays during construction. Flaggers will direct traffic.
- Project is expected to take up to 2 months to complete.
Current activities
- County seeking construction proposals
Funding
- Project estimate $180,000.00
- Funding is provided from Community Road Fund and developer contributions