Oregon Trail Elementary Flashing Crosswalk Improvements

Status

Preparing for construction

Updated: July 16, 2026

Project description

Install a flashing crosswalk at the intersection of Oregon Trail Elementary and 152nd Ave in the Oregon City area.  Improvements will also include new safety signs, pavement markings and street lighting.

Schedule

  • Construction: August 2026 – October 2026

Traffic impact

  • Expect shoulder and lane closures with minimal delays during construction. Flaggers will direct traffic.
  • Project is expected to take up to 2 months to complete.

Current activities

  • County seeking construction proposals

Funding

  • Project estimate $180,000.00
  • Funding is provided from Community Road Fund and developer contributions
Contact
Department Staff
Mike Oleson
503-706-6635

Phone:503-742-4691
Email:engineering@clackamas.us

150 Beavercreek Road Room #325 Oregon City, OR 97045

Office Hours:

Monday to Thursday
8 a.m. to 4 p.m.

Available by phone/email
Friday
8 a.m. to 3 p.m.