Public Housing Update

January 2026

Public Housing Repositioning

Scattered Sites: Be on the lookout for a letter with information about next steps for relocation, including when you can expect to move and how staff will support you.

Hillside Park Phase 2: As a reminder, everyone must be moved out by March 31st, 2026. If you are expecting to receive a Voucher and do not currently have one, please reach out to Ashley Ferron at: 
Email: HACC-Relocation@Clackamas.us 
Phone: 503-867-7484 (text friendly)

Oregon City View Manor: We are working with HUD to determine when relocation can begin and will share updates as they are available. All OCVM residents who want to move to the Clackamas Heights Redevelopment will be provided the opportunity.

Questions?

Relocation Questions:
Ashley Ferron
aferron@clackamas.us
503-867-7487
Relocation Counselor:
Charity Joswick
Charity@magikcorp.com
503-270-6576
All Other Questions:
Gloria LaFleur
HACC Housing Developer
GLaFleur@Clackamas.us
971-930-3184

Affordable Homeownership Opportunity

Shortstack Milwaukie is Clackamas County’s first homeownership project funded by the Regional Housing Bond. It includes 15 two-bedroom homes, each listed under $265,000, that are affordable to households earning up to 80% of the Area Median Income.

Find available homes.

Applications are now being accepted through Proud Ground on a first-come, first-served basis. Applications

Shortstack Milwaukie Exterior Shortstack Milwaukie Interior Kitchen

Clackamas Heights Redevelopment

Construction Update and What to Expect Construction at the site began in November 2025 and is expected to continue for about two years. Below is a snapshot of what’s happening now and what’s coming up:

  • Demolition: Currently underway and expected to be finished by the end of January.
  • Site and utility work: Continuing through March to prepare the site and underground utilities for new buildings.
  • Foundation work: Planned to begin in April, marking the start of new building construction.

We’ll continue to share updates as work progresses.

Hillside Park Construction

Lease-up has been steadily progressing with 13 households moved in and six additional households completing their orientation process.

To learn more

The first phase of redevelopment will conclude with Parkside Heights East and West which are scheduled for completion in the spring.

Hillside Park Apartments exterior Hillside Park Apartments interior kitchen

View the Latest Development Updates Here:

Clackamas Heights 
Hillside Park
Oregon City View Manor
Scattered Site

Phone:503-655-8267
Fax:503-655-8676
Email:hacc@clackamas.us

13930 Gain St Oregon City, OR 97045

Office Hours:

Monday to Thursday
8 a.m. to 5 p.m.
By appointment only after 5 p.m.

After Hours Maintenance Emergency:
503-780-3896

Maintenance (Monday - Thursday):
503-650-3535