Our fee schedule and tools are meant to assist you in estimating building fees.
Actual building fees vary from project to project. Final project fees may include items we collect on behalf of other agencies, e.g. 12% of all fees collected are returned to the State.
Additionally, projects within the City of Canby use their adopted fee schedule.
We will discuss specific fees with you when you submit your plans or application.
Fee schedules
- General Inspections
- Heating, Ventilating and Air Conditioning (HVAC)
- Manufactured Dwellings, Park Trailers, Cabanas
- Electrical
- Commercial/Industrial Structural Code
- 1- and 2-Family Structural
- Plumbing
Fees
| Service or item | Fee Amount |
|---|---|
| All Collected Fees | 12% are returned to the State |
| Inspections outside normal business hours (minimum charge 4 hours) | $120/hr + OT |
| Reinspection fees | $120/hr |
| Inspections for which no fee is specifically indicated (min. ½ hour) | $120/hr |
| Add'l plan review required by change, additions, or revisions to approve plans (min. charge 1 hour) | $120/hr |
| Residential Certificate of Occupancy (charged at time of permit issuance) | $42.50 |
| Temporary Certificate of Occupancy (commercial) | $120 /hr with min. 2 hr chrg. |
| Certificate of Occupancy (commercial) | $120 /hr with min. 2 hr chrg. |
| 1 & 2 Family Mechanical Minimum permit fee & reinspection fee | $120 |
| For each supplemental permit | $21 |
| Minor Label Re-inspection | $75 |
| Phased Project Fee | $250 + 10% of the total project building permit fee. |
| $1,500 (Not to exceed value for each phase) | |
| Deferred Submittal | $250 Minimum fee; 65% of the permit fee according to OAR 918-050-0110 (2)(3) using the value of the particular deferred portion or portions of the project. This fee is in addition to the project plan review fee based on the total project value. |
| Hourly rate for any plumbing, electrical, building or manufactured dwelling permit regardless of type | $120/hr |
| Reactivation of any plumbing, electrical, building or manufactured dwelling permit | |
| Expired up to one year | 50% of New permit fee |
| Any permit expired more than one year | 100% of New permit fee |
HVAC
| Service or item | Fee Amount |
|---|---|
| Air Conditioner | $18 |
| Fire/Smoke Dampers/duct smoke detectors | $12 |
| Heat Pump | $18 |
| Install/replace/relocate heaters-suspended, wall or floor mounted | $18 |
| Environmental exhaust & ventilation: | |
| Appliance vent | $12 |
| Exhaust fan | $9 |
| Dryer Exhaust | $9 |
| Kitchen Exhaust | $12 |
| Other appliance/equipment: | |
| Decorative fireplace | $18 |
| Insert-type | $18 |
| Woodstove/Pellet Stove | $18 |
| HVAC Air Handling Unit | |
| 0-10K CFM | $12 |
| over 10K CFM | $23 |
| Boiler/Compressor | |
| Boiler not to exceed 1.5 cubic feet | $18 |
| Furnace | |
| to 100K BTU | $18 |
| >100K BTU | $23 |
| Fuel Piping | |
| 0 – 4 outlets | $5 |
| each additional (4 or more outlets requires a schematic) | $2 |
| Other | |
| Water Heater | $9 |
| Cooktop | $12 |
| Gas logs | $12 |
| Fuel Gas Regulators | $12 |
| Mechanical Commercial | $120 Minimum + fee based on valuations listed below |
| Based on Valuation Minimum | |
| $1 - $5,000 | $120 |
| $5,001 - $10,000 | $120 + $1.66 per $100 over $5,000 |
| $10,001 to $100,000 | $203 + $12.34 per $1,000 over $10,000 |
| $100,000 + | $1,314 + $8.47 per $1,000 over $100,000 |
| Commercial Plan Review | 25% of permit fee |
Manufactured Dwellings, Park Trailers, Cabana Fees
| Service or item | Fee Amount |
|---|---|
| Site installation/set up fee for manufactured dwelling, park trailer or cabana | $407 |
| Earthquake Resistant Bracing system installation fee. In addition to site installation fee described above. | $103 |
| Reinspection fee per each inspection. Fee must be paid prior to next inspection | $120 |
| Installations w/o permits | Actual cost of investigation |
| Inspections outside normal business hours. Min. of four hours OT rate | $120/hr + OT |
| Oregon Mfg. Dwelling Standard Publication. Required when no installer is involved. | $12 |
| Mobile Home Park construction & recreational park development | Varies w/ number of spaces |
Electrical Fees
| Service or item | Fee Amount |
|---|---|
| Fee includes a prescribed number of inspections. See Electrical Permit application for quantities. | |
| Electrical plan review is required for new construction and alterations in the following locations per OAR 918-311-0040: | 25% of Permit fee |
| A. Service or feeder beginning at 400 amps with available fault current greater than 10,000 amps at 150 volts or less to ground or any system greater than 14,000 volts | |
| B. Installation of a 150 KVA or larger separately derived system per Article 100 of the NEC | |
| C. Addition of a new motor load greater than 100 HP or more | |
| D. Fire pump installations as defined in Article 695 of the NEC | |
| E. Emergency systems installations as defined in Article 700 of the NEC | |
| F. 6 or more residential units in one structure or any A, E, 1-2 or 1-3 occupancies as defined in the Oregon Structural Speciality Code | |
| G. Service or feeder rated at 60 amps or over | |
| H. System over 600 supply volts nominal | |
| I. Building more than 3 stories in height | |
| J. Building over 10,000 sq. ft. | |
| K. Occupant load over 99 persons | |
| L. Manufactured Structures Park or Recreational Vehicle Park; new addition or alterations | |
| M. Classified area or structure containing special occupancy as described in NEC Chapter 5 | |
| Residential single-or multi-family dwelling units including attached garages and covered areas not more than 1,000 sq. ft. | $270 |
| Each additional 500 Sq. ft. | $55 |
| Limited energy: up to two inspections only | $109 |
| Limited Energy, Residential | $109 |
| Limited Energy, Multi-family | $109 |
| Note: This fee covers all limited energy systems in residential occupancies when installed at the same time by the permittee. Installations such as antenna wire, computer wire, and alarm wire done by other contractors require separate permits and fees. No limited energy permit is required if the original permittee installs wire for doorbells, garage door openers, and heating & air conditioning controls | |
| Manufactured Home Service or feeder | $109 |
| Temp. Const. Service, Feeder | |
| Less than 200 amps | $94 |
| 201-400 amps | $200 |
| 401-600 amps | $270 |
| 601-1000 amps | $482 |
| >1000 amps | $882 |
| Permanent Service, Feeder | |
| <200 amps | $161 |
| 201-400 amps | $213 |
| 401-600 amps | $321 |
| 601-1000 amps | $482 |
| >1000 amps | $882 |
| Service Reconnect only | $109 |
| Branch Circuits-new, alteration, extension per panel | |
| With purchase service or feeder | $12 |
| Without purchase service or feeder: | |
| First circuit | $90 |
| Each additional | $12 |
| Renewable Electrical Energy | |
| 5 kva or less (2) | $144 |
| 5.01 to 15 kva (2) | $169 |
| 15.01 to 25 kva (2) | $280 |
| Misc. fees, hourly rate | $120 |
| Each additional inspection | $120 |
| Special Fees | |
| Water/sewer pump; Septic circuit | $109 |
| Sign/Outline Lighting | $109 |
| Signal Circuit/Limited Energy panel, alteration or extension | $109 |
| Minimum permit fee and reinspection fee | $120 |
| Master Permit Fee per hour (aka Electrical in-plant inspections) | $120 /hour |
Structural Codes (Commercial/Industrial)
| Service or item | Fee Amount |
|---|---|
| Fire & life safety plan review | 65% of building permit fee |
| In conjunction with regular plan review | 35% of building permit fee |
| Independently | 40% of building permit fee |
| $1 - $2,000 | $120 |
| $2,001 - $25,000 | $120 + $7.40 per $1,000 over $2,000 |
| $25,001 - $50,000 | $290 + $6.72 per $1,000 over $25,000 |
| $50,001 to $100,000 | $458 + $4.48 per $1,000 over $50,000 |
| $100,001 + | $682 + $3.75 per $1,000 over $100,000 |
Structural Codes (1&2 Family)
| Service or item | Fee Amount |
|---|---|
| New Construction, Additions, Remodels, Alterations | |
| Regular plan review | 65% of building permit fee |
| $1 - $500 | $120 |
| $501 - $2,000 | $120 |
| $2,001 - $25,000 | $120 + $7.40 per $1,000 over $2,000 |
| $25,001 - $50,000 | $290 + $6.72 per $1,000 over $25,000 |
| $50,001 to $100,000 | $458 + $4.48 per $1,000 over $50,000 |
| $100,000 + | $682 + $3.75 per $1,000 over $100,000 |
Plumbing
| Service or item | Fee Amount |
|---|---|
| Minimum Permit Fee | $120 |
| Plumbing plan review is required for new construction and alterations in the following locations per OAR 918-780-0040: Medical gas and vacuum systems in health care facilities; Chemical drain, waste, and vent systems; Sewer waste water pretreatment systems; Vacuum drainage, waste and vent systems; Reclaimed waste water systems; Commercial potable water pressure booster pumps for water supplied by a municipality; Building water service lines with an interior diameter of 2 inches or larger (2 inch water service stamped by professional engineer is exempt); Residential multi-purpose fire sprinkler systems. | 0.25 |
| 1 & 2 family dwellings | |
| 1 bath | $761 |
| 2 baths | $864 |
| 3 baths | $956 |
| each additional bathroom or half | $87 |
| each additional kitchen | $87 |
| Note: These fees include rainwater disposal system, including leaders & drains to approved disposal area, plumbing fixtures or waste discharging devices, including drain, waste & vent piping, water piping, hot water heaters, the first 100 ft of water service & sanitary sewer line & under floor low point drain. | |
| Sanitary Sewer | $145 |
| Water closet | $31 |
| Shower bath | $31 |
| Bathtub | $31 |
| Basin, Lav. | $31 |
| Sink, kitchen | $31 |
| Dishwasher | $31 |
| Disposal | $31 |
| Clothes Washer | $31 |
| Water Heater | $31 |
| Laundry Tray or Service Sink | $31 |
| Floor Drains | $31 |
| Bar Sinks | $31 |
| Ice Maker | $31 |
| House moves (not including storm, sanitary sewer or water service inspection | $91 |
| Prefabricated Commercial Structures (not including storm or sanitary sewer, or water service inspection | $182 |
| Hub/Case Drain | $31 |
| Floor sinks | $31 |
| Drinking Fountain | $31 |
| Urinals/Toilets | $31 |
| Water System; Interior Water Re-Pipe; Building Drain Replacement | |
| - First 100 ft. | $100 |
| - Additional 100 ft. between 101 ft and 200 ft in length | $100 |
| - Each additional 100 ft. above 200 ft in length | $25 |
| Storm Sewer | |
| - First 100 ft or less | $110 |
| - Each additional 100 ft. | $74 |
| Sanitary Sewer | |
| - 150 ft or less total length | $145 |
| - Over 150 ft. total length: | |
| - First 50 ft. | $110 |
| - Each additional | $74 |
| Septic tank connnection | |
| - First 50 ft. or less | $110 |
| - Additional 100 ft. | $74 |
| Roof Drains – (Commercial leader or conductor) | $19 |
| Roof Drain Package – Residential & Duplex | $182 |
| 1/2 Roof Drain Package | $91 |
| Trap Primers (1-5) | $31 |
| Trap Primers (over 5, each additional) | $5 each |
| Catch Basins (area drains) | $31 |
| Backflow prevention devices | $31 |
| Interceptors, grease, etc. | $31 |
| Miscellaneous | $31 |
| Drywells/leach line/trench drain | $31 |
| Manufactured home utilities | $126 |
| Manholes | $31 |
| Absorption valves | $31 |
| Backflow preventer | $31 |
| Backwater valve | $31 |
| Ejectors/sump | $31 |
| Expansion tanks (devices) | $31 |
| Fixture/sewer cap | $31 |
| Floor drains/floor sinks/hub | $31 |
| Hose bib | $31 |
| Sump | $31 |
| Plumbing Medical Gas Installation | $121 plus a fee based on installation costs listed below |
| Fees shall be determined based on the value of the medical gas equipment & installation costs | |
| $1 to $5,000 | $121 minimum fee |
| $5,001 - $10,000 | $121 + $1.82 each add'l $100 over $5,000 |
| $10,001 to $100,000 | $212 + $12.34 for each additional $1,000 over $10,000 |
| $100,001 and above | $1,322.60 + $8.47 for each additional $1,000 over $100,000 |
| Plan Review | 50% of the installation permit fee |
| Residential Fire Suppression Systems | |
| Multi-purpose or continuous loop systems | |
| 0 - 2,000 sq. ft. | $105 |
| 2,001 - 3,600 sq. ft. | $156 |
| 3,601 – 7,200 sq. ft. | $198 |
| > 7,201 sq. ft (includes Plan Review fee) | $242 |
| Stand Alone Systems | |
| 0 – 2,000 sq. ft | $198 |
| 2,001 - 3,600 sq. ft. | $283 |
| 3,601 - 7,200 sq. ft | $327 |
| > 7,201 sq. ft & greater (includes Plan Review fee) | $368 |
| Fees for partial installations shall be based on the square footage of the area in which the fire suppression is to be installed. Fees for stand-alone systems do not include required backflow prevention device. A separate fee is required for this installation. |
Fines
General Transportation & Development Fees
| Service or item | Fee Amount |
|---|---|
| Fee Appendix A - Annual CPI Adjustment [Applies to all DTD Division Fees, unless otherwise noted.] | Annual adjustment; change in Consumer Price Index for the Western United States (CPI) up to 3%. - Fee ≤$10: EXEMPT from annual CPI adjustment - Fee $10.01-$50: Round DOWN to nearest $0.25 - Fee >$50.01: Round DOWN to nearest $1 |
| Research/Consultation fee | $123/hour - 1 hour minimum |
| Paper copies | |
| 8 1/2" x 11" or 14" | $2/page |
| 11" x 17" | $2.50/page |
| 18" x 24" | $3.50/page |
| Large Format | $0.75/sq ft ($5 minimum) |
| Bank Managed Service Fee | Actual cost |
| Returned check fee | $25.50 |
| Vehicle registration fee | |
| - Motorcycles/mopeds | $15 per year |
| - Utility/Light Trailer | $5 per year |
| - All other vehicles not otherwise exempt | $30 per year |
| Technology Fee | 3% of permit fee; maximum $5/permit |
Translate