Building Fees

Our fee schedule and tools are meant to assist you in estimating building fees.

Actual building fees vary from project to project. Final project fees may include items we collect on behalf of other agencies, e.g. 12% of all fees collected are returned to the State.

Additionally, projects within the City of Canby use their adopted fee schedule.

We will discuss specific fees with you when you submit your plans or application.

Fee schedules

Fees

Service or itemFee Amount
All Collected Fees12% are returned to the State
Inspections outside normal business hours (minimum charge 4 hours)$120/hr + OT
Reinspection fees$120/hr
Inspections for which no fee is specifically indicated (min. ½ hour)$120/hr
Add'l plan review required by change, additions, or revisions to approve plans (min. charge 1 hour)$120/hr
Residential Certificate of Occupancy (charged at time of permit issuance)$42.50
Temporary Certificate of Occupancy (commercial)$120 /hr with min. 2 hr chrg.
Certificate of Occupancy (commercial)$120 /hr with min. 2 hr chrg.
1 & 2 Family Mechanical Minimum permit fee & reinspection fee$120
For each supplemental permit$21
Minor Label Re-inspection$75
Phased Project Fee$250 + 10% of the total project building permit fee.
 $1,500 (Not to exceed value for each phase)
Deferred Submittal$250 Minimum fee; 65% of the permit fee according to OAR 918-050-0110 (2)(3) using the value of the particular deferred portion or portions of the project. This fee is in addition to the project plan review fee based on the total project value.
Hourly rate for any plumbing, electrical, building or manufactured dwelling permit regardless of type$120/hr
Reactivation of any plumbing, electrical, building or manufactured dwelling permit 
Expired up to one year50% of New permit fee
Any permit expired more than one year100% of New permit fee

HVAC

Service or itemFee Amount
Air Conditioner$18
Fire/Smoke Dampers/duct smoke detectors$12
Heat Pump$18
Install/replace/relocate heaters-suspended, wall or floor mounted$18
Environmental exhaust & ventilation: 
Appliance vent$12
Exhaust fan$9
Dryer Exhaust$9
Kitchen Exhaust$12
Other appliance/equipment: 
Decorative fireplace$18
Insert-type$18
Woodstove/Pellet Stove$18
HVAC Air Handling Unit 
0-10K CFM$12
over 10K CFM$23
Boiler/Compressor 
Boiler not to exceed 1.5 cubic feet$18
Furnace 
to 100K BTU$18
>100K BTU$23
Fuel Piping 
0 – 4 outlets$5
each additional (4 or more outlets requires a schematic)$2
Other 
Water Heater$9
Cooktop$12
Gas logs$12
Fuel Gas Regulators$12
Mechanical Commercial$120 Minimum + fee based on valuations listed below
Based on Valuation Minimum 
$1 - $5,000$120
$5,001 - $10,000$120 + $1.66 per $100 over $5,000
$10,001 to $100,000$203 + $12.34 per $1,000 over $10,000
$100,000 +$1,314 + $8.47 per $1,000 over $100,000
Commercial Plan Review25% of permit fee

Manufactured Dwellings, Park Trailers, Cabana Fees

Service or itemFee Amount
Site installation/set up fee for manufactured dwelling, park trailer or cabana$407
Earthquake Resistant Bracing system installation fee. In addition to site installation fee described above.$103
Reinspection fee per each inspection. Fee must be paid prior to next inspection$120
Installations w/o permitsActual cost of investigation
Inspections outside normal business hours. Min. of four hours OT rate$120/hr + OT
Oregon Mfg. Dwelling Standard Publication. Required when no installer is involved.$12
Mobile Home Park construction & recreational park developmentVaries w/ number of spaces

Electrical Fees

Service or itemFee Amount
Fee includes a prescribed number of inspections. See Electrical Permit application for quantities. 
Electrical plan review is required for new construction and alterations in the following locations per OAR 918-311-0040:25% of Permit fee
A. Service or feeder beginning at 400 amps with available fault current greater than 10,000 amps at 150 volts or less to ground or any system greater than 14,000 volts 
B. Installation of a 150 KVA or larger separately derived system per Article 100 of the NEC 
C. Addition of a new motor load greater than 100 HP or more 
D. Fire pump installations as defined in Article 695 of the NEC 
E. Emergency systems installations as defined in Article 700 of the NEC 
F. 6 or more residential units in one structure or any A, E, 1-2 or 1-3 occupancies as defined in the Oregon Structural Speciality Code 
G. Service or feeder rated at 60 amps or over 
H. System over 600 supply volts nominal 
I. Building more than 3 stories in height 
J. Building over 10,000 sq. ft. 
K. Occupant load over 99 persons 
L. Manufactured Structures Park or Recreational Vehicle Park; new addition or alterations 
M. Classified area or structure containing special occupancy as described in NEC Chapter 5 
Residential single-or multi-family dwelling units including attached garages and covered areas not more than 1,000 sq. ft.$270
Each additional 500 Sq. ft.$55
Limited energy: up to two inspections only$109
Limited Energy, Residential$109
Limited Energy, Multi-family$109
Note: This fee covers all limited energy systems in residential occupancies when installed at the same time by the permittee. Installations such as antenna wire, computer wire, and alarm wire done by other contractors require separate permits and fees. No limited energy permit is required if the original permittee installs wire for doorbells, garage door openers, and heating & air conditioning controls 
Manufactured Home Service or feeder$109
Temp. Const. Service, Feeder 
Less than 200 amps$94
201-400 amps$200
401-600 amps$270
601-1000 amps$482
>1000 amps$882
Permanent Service, Feeder 
<200 amps$161
201-400 amps$213
401-600 amps$321
601-1000 amps$482
>1000 amps$882
Service Reconnect only$109
Branch Circuits-new, alteration, extension per panel 
With purchase service or feeder$12
Without purchase service or feeder: 
First circuit$90
Each additional$12
Renewable Electrical Energy 
5 kva or less (2)$144
5.01 to 15 kva (2)$169
15.01 to 25 kva (2)$280
Misc. fees, hourly rate$120
Each additional inspection$120
Special Fees 
Water/sewer pump; Septic circuit$109
Sign/Outline Lighting$109
Signal Circuit/Limited Energy panel, alteration or extension$109
Minimum permit fee and reinspection fee$120
Master Permit Fee per hour (aka Electrical in-plant inspections)$120 /hour

Structural Codes (Commercial/Industrial)

Service or itemFee Amount
Fire & life safety plan review65% of building permit fee
In conjunction with regular plan review35% of building permit fee
Independently40% of building permit fee
$1 - $2,000$120
$2,001 - $25,000$120 + $7.40 per $1,000 over $2,000
$25,001 - $50,000$290 + $6.72 per $1,000 over $25,000
$50,001 to $100,000$458 + $4.48 per $1,000 over $50,000
$100,001 +$682 + $3.75 per $1,000 over $100,000

Structural Codes (1&2 Family)

Service or itemFee Amount
New Construction, Additions, Remodels, Alterations 
Regular plan review65% of building permit fee
$1 - $500$120
$501 - $2,000$120
$2,001 - $25,000$120 + $7.40 per $1,000 over $2,000
$25,001 - $50,000$290 + $6.72 per $1,000 over $25,000
$50,001 to $100,000$458 + $4.48 per $1,000 over $50,000
$100,000 +$682 + $3.75 per $1,000 over $100,000

Plumbing

Service or itemFee Amount
Minimum Permit Fee$120
Plumbing plan review is required for new construction and alterations in the following locations per OAR 918-780-0040: Medical gas and vacuum systems in health care facilities; Chemical drain, waste, and vent systems; Sewer waste water pretreatment systems; Vacuum drainage, waste and vent systems; Reclaimed waste water systems; Commercial potable water pressure booster pumps for water supplied by a municipality; Building water service lines with an interior diameter of 2 inches or larger (2 inch water service stamped by professional engineer is exempt); Residential multi-purpose fire sprinkler systems.0.25
1 & 2 family dwellings 
1 bath$761
2 baths$864
3 baths$956
each additional bathroom or half$87
each additional kitchen$87
Note: These fees include rainwater disposal system, including leaders & drains to approved disposal area, plumbing fixtures or waste discharging devices, including drain, waste & vent piping, water piping, hot water heaters, the first 100 ft of water service & sanitary sewer line & under floor low point drain. 
Sanitary Sewer$145
Water closet$31
Shower bath$31
Bathtub$31
Basin, Lav.$31
Sink, kitchen$31
Dishwasher$31
Disposal$31
Clothes Washer$31
Water Heater$31
Laundry Tray or Service Sink$31
Floor Drains$31
Bar Sinks$31
Ice Maker$31
House moves (not including storm, sanitary sewer or water service inspection$91
Prefabricated Commercial Structures (not including storm or sanitary sewer, or water service inspection$182
Hub/Case Drain$31
Floor sinks$31
Drinking Fountain$31
Urinals/Toilets$31
Water System; Interior Water Re-Pipe; Building Drain Replacement 
- First 100 ft.$100
- Additional 100 ft. between 101 ft and 200 ft in length$100
- Each additional 100 ft. above 200 ft in length$25
Storm Sewer 
- First 100 ft or less$110
- Each additional 100 ft.$74
Sanitary Sewer 
- 150 ft or less total length$145
- Over 150 ft. total length: 
- First 50 ft.$110
- Each additional$74
Septic tank connnection 
- First 50 ft. or less$110
- Additional 100 ft.$74
Roof Drains – (Commercial leader or conductor)$19
Roof Drain Package – Residential & Duplex$182
1/2 Roof Drain Package$91
Trap Primers (1-5)$31
Trap Primers (over 5, each additional)$5 each
Catch Basins (area drains)$31
Backflow prevention devices$31
Interceptors, grease, etc.$31
Miscellaneous$31
Drywells/leach line/trench drain$31
Manufactured home utilities$126
Manholes$31
Absorption valves$31
Backflow preventer$31
Backwater valve$31
Ejectors/sump$31
Expansion tanks (devices)$31
Fixture/sewer cap$31
Floor drains/floor sinks/hub$31
Hose bib$31
Sump$31
Plumbing Medical Gas Installation$121 plus a fee based on installation costs listed below
Fees shall be determined based on the value of the medical gas equipment & installation costs 
$1 to $5,000$121 minimum fee
$5,001 - $10,000$121 + $1.82 each add'l $100 over $5,000
$10,001 to $100,000$212 + $12.34 for each additional $1,000 over $10,000
$100,001 and above$1,322.60 + $8.47 for each additional $1,000 over $100,000
Plan Review50% of the installation permit fee
Residential Fire Suppression Systems 
Multi-purpose or continuous loop systems 
0 - 2,000 sq. ft.$105
2,001 - 3,600 sq. ft.$156
3,601 – 7,200 sq. ft.$198
> 7,201 sq. ft (includes Plan Review fee)$242
Stand Alone Systems 
0 – 2,000 sq. ft$198
2,001 - 3,600 sq. ft.$283
3,601 - 7,200 sq. ft$327
> 7,201 sq. ft & greater (includes Plan Review fee)$368
Fees for partial installations shall be based on the square footage of the area in which the fire suppression is to be installed. Fees for stand-alone systems do not include required backflow prevention device. A separate fee is required for this installation. 

Fines

General Transportation & Development Fees

Service or itemFee Amount
Fee Appendix A - Annual CPI Adjustment  

[Applies to all DTD Division Fees, unless otherwise noted.]
Annual adjustment; change in Consumer Price Index for the Western United States (CPI) up to 3%.  

- Fee ≤$10: EXEMPT from annual CPI adjustment  
- Fee $10.01-$50: Round DOWN to nearest $0.25  
- Fee >$50.01: Round DOWN to nearest $1
Research/Consultation fee$123/hour - 1 hour minimum
Paper copies 
8 1/2" x 11" or 14"$2/page
11" x 17"$2.50/page
18" x 24"$3.50/page
Large Format$0.75/sq ft ($5 minimum)
Bank Managed Service FeeActual cost
Returned check fee$25.50
Vehicle registration fee 
- Motorcycles/mopeds$15 per year
- Utility/Light Trailer$5 per year
- All other vehicles not otherwise exempt$30 per year
Technology Fee3% of permit fee; maximum $5/permit