Two culverts carrying Conway Creek under Aschoff Road in the Rhododendron area are damaged, undersized, and do not easily allow fish and wildlife passage. These culverts will be replaced with a modular bridge.
Design phase
Updated: Nov. 3, 2026
Why
To minimize potential impacts to the roadway due to flooding and to provide access for fish and other aquatic organisms to reach upstream cold-water habitat.
Schedule
- Design: January 2026 to September 2027
- Right-of-way: July 2026 to June 2027
- Construction: July 2028 to December 2028
Traffic impact
- Partial one-day closures are anticipated during installation of bridge beams.
- Project is expected to take up to 3 months to complete.
- Culvert work limited to a state-approved in-water work period of July 15 to August 31.
Current activities
- Project in design phase
Funding
- Project estimate $1.9 million.
- Funding is provided from Federal Culvert AOP grant funds and county road funds.