Two culverts carrying Conway Creek under Aschoff Road in the Rhododendron area are damaged, undersized, and do not easily allow fish and wildlife to pass upstream and will be replaced with a modular bridge.
Design phase
Updated: April 16, 2026
Why
Why
To minimize potential impacts to the roadway due to flooding and to provide access for fish and other aquatic organisms to reach upstream cold-water habitat.
Schedule
- Design: January 2026 to September 2027
- Right-of-way: July 2026 to June 2027
- Construction: July 2028 to December 2028
Traffic impact
- A road closure will be needed during construction.
- Project is expected to take up to 3 months to complete.
- Culvert work limited to a state-approved in-water work period of July 15 to August 31.
Current activities
- Project in design phase
Funding
- Project estimate $1.9 million.
- Funding is provided from Federal Culvert AOP grant funds and county road funds.