Laurie Ave Stormwater Improvements

Status

Coordinating construction

Updated: Feb. 24, 2025

Extending Stormwater Infrastructure to Laurie Ave.

The project will install a new 12-inch diameter stormwater main on 436 feet of Laurie Avenue south of Courtney Ave and 6 catch basins to reduce the frequency of flooding. Additionally, 300 feet of stormwater main on Courtney Avenue west of Laurie Avenue will be replaced with 12-inch diameter stormwater pipe. 

Why

The new stormwater main and catch basins are expected to reduce flooding and convey a 10-year storm event.

Schedule

  • Design: June 2023 to April 2024
  • Construction: March 2025 to July 2025

Traffic impact

Construction is planned to start Monday, March 10, 2025. Expect delays on Laurie Ave and Courtney Ave between 7 a.m. and 6 p.m.

 

Current activities

Surveying and design services. 

Funding

  • Project estimate $800,000.
  • Funding is from county road funds.

Phone:503-742-4691
Email:engineering@clackamas.us

150 Beavercreek Road Room #325 Oregon City, OR 97045

Office Hours:

Monday to Thursday
8 a.m. to 4 p.m.

Available by phone/email
Friday
8 a.m. to 3 p.m.

Related News
Transportation and Development, Transportation Engineering, Transportation Maintenance, Parks, Building Codes, Dog Services, Code Enforcement, Library, Planning and Zoning, Septic and Onsite Wastewater Systems, County Surveyor's Office, Development Services, Development Engineering