In early 2021, heavy rains and strong winds toppled trees, causing the slope to collapse next to Rugg Road near the Hideaway Court intersection in the Boring area. A retaining wall will be built at this location.
Temporary protective sheeting and plant seeding are in place until permanent repairs are constructed.
Project design complete
Updated: May 17, 2023
Why
To stabilize the slope next to Rugg Road.
Schedule
- Design: March 2021 - March 2022
- Construction: To be determined
Traffic impacts
Single-lane closures will be needed during construction. A temporary road closure is anticipated for 3–4 weeks to build the wall.
Current activities
Project design complete.
Funding
- Project estimate $930,000
- Funding is provided from Damascus road funds