SE 90th Avenue Reconstruction

Project description: Total reconstruction of SE 90th Avenue between SE Monterey Ave and SE Causey Ave due to poor roadway condition that requires ongoing maintenance. Includes improved lighting, storm drainage and ADA ramps.

Updated: 3/4/20

Status: In design

Schedule:

  • Construction start: May 2020
  • Construction complete: Dec. 2020

Contact: Jonathan Hangartner, PE, Project Manager, jhangartner@clackamas.us, 503-742-4649

Things to be aware of:

  • The road will be completely closed during construction to vehicles, bicycles and pedestrians. No parking along SE 90th Ave will be allowed for the duration of the project. 

Current activities:

  • Design of roadway reconstruction, stormwater facilities, ADA ramps, and street lights.

Funding:

  • Project estimate is $1,171,000
  • Funding is provided from County Road Fund and fees charged to developers.

 

    Phone:503-742-4691
    Email:engineering@clackamas.us

    150 Beavercreek Road Room #325 Oregon City, OR 97045

    Office Hours:

    ⚠ Due to COVID-19, our offices are closed to the public. At this time the closure is expected to continue through April 20. Our employees are available and working to meet your needs remotely.