72nd / Luther Safety Improvements

Traffic engineers evaluated operations for vehicles, pedestrian and bicycles and identified low-cost improvements to reduce the number and severity of crashes at the intersection. The intersection will converted to an all-way stop. The intersection at Bell and Alberta will also be reconfigured.

Status

Complete

Updated: March 15, 2023

Why

To reduce crashes and improve safety for all roadway users.

Schedule

  • Design: July 2021 - Jan. 2023
  • Construction: March 2023 - May 2023

Funding

  • Project estimate $27,000.
  • Funding is provided from county road funds and HB2017 state gas taxes. 
Contact
Department Staff
Christian Snuffin
Transportation and Development
503-742-4716

Phone:503-742-4691
Email:engineering@clackamas.us

150 Beavercreek Road Room #325 Oregon City, OR 97045

Office Hours:

Monday to Thursday
8 a.m. to 4 p.m.

Available by phone/email
Friday
8 a.m. to 3 p.m.

Related News
Transportation and Development, Transportation Engineering, Transportation Maintenance, Parks, Building Codes, Dog Services, Code Enforcement, Library, Planning and Zoning, Septic and Onsite Wastewater Systems, County Surveyor's Office, Development Services, Development Engineering