This technology infrastructure project will help connect ferry riders with information on the operating status of the ferry.
Updated: March 27, 2024
The project includes:
- Extending fiber optic cable to the ferry location to provide wireless connection to electronic signs
- Adding cameras at the ferry landings for images to be viewed on the website and ODOT TripCheck
- Upgrading signs with wireless and electrical connection to display both open and closed status at four locations, and adding a fifth sign on Territorial Road west of Hwy 99E
- Adding access to sign status through a phone app
- Transitioning to fare collection by credit card instead of cash
Current activities
Installing fiber optic cable to the ferry signals.
Schedule
- Design: Dec. 2016 - March 2023
- Right of way: April 2018 - June 2023
- Construction: March 2023 - June 2024
Project impact on traffic
- No road closures are expected during construction, although there may be delays up to 20 minutes near Advance Road or the ferry boat landings.
Funding
- Estimated total project cost: $1 million
- Funded through federal Ferry Boat Discretionary Funds matched with county road funds