82nd Dr/Jennifer St traffic signal replacement

Status

Project is in design phase.

Updated: Aug. 8, 2023

Replace the damaged signal pole at the southwest corner of 82nd Dr and Jennifer St. Includes replacing all signal poles, adding mast arms and signal heads, repaving the intersection, reconstructing all curb ramps to meet ADA requirements and adding pedestrian push buttons.

Why

To maintain regional traffic signal connection and to improve pedestrian access.

Schedule

  • Design: Sept 2023-winter 2024
  • Construction: spring 2025- winter 2025

Current activities

  • Selected DKS as the consultant for project design

Traffic impact

  • Minor and intermittent lane closures for traffic signal upgrades will be needed.

Funding

  • Project estimate $1.4 million
  • Funding is provided from the county road funds
Contact
Department Staff
Mike Ward
Project manager
503-742-4688

Phone:503-742-4691
Email:engineering@clackamas.us

150 Beavercreek Road Room #325 Oregon City, OR 97045

Office Hours:

Monday to Thursday
8 a.m. to 4 p.m.

Available by phone/email
Friday
8 a.m. to 3 p.m.

Related Events
Transportation Maintenance, Transportation and Development, Transportation Engineering
-
Related News
DTD, Library District, Development Agency, Transportation Engineering